To the best of my knowledge, they haven't even applied for the permit, and they should have done that 3 weeks ago for temporary power and asbestos abatement. Now the city employees are a skeleton crew so who knows when the permit will be issued. As soon as I signed to work authorization the general permit process should have been started, that was over a month ago.
The project manager is very new, and from what I understand this is his first job on his own. So far I'm not impressed and have been in contact with his boss. I doubt we will be able to move in by the end of the year at this point unless the pace picks up real fast.
Meanwhile I'm paying a mortgage and rent.